Wharf Tunnel Repairs Phase 1 - Feb 26 (3)
 

 What's Happening Now?

 

Phase 1: Byers Street  tunnel repair work is underway. 

Crews are onsite and set up in the eastern portion of the Wharf Parking Lot to repair the creek tunnel that runs under Byers Street. This phase of the project is expected to continue into August or September.

Project Overview

The City of Staunton is undertaking a critical infrastructure project to repair the aging stormwater tunnels beneath Byers Street, West Johnson Street, and New Street. Addressing these conditions now is essential to prevent structural failure and ensure public safety in the Wharf District.

  • Duration: February 2026 – Spring 2027

  • Investment: $4.62 Million

  • Goal: Restore structural integrity of tunnels supporting roadways while maintaining downtown access.

  • Method: "Top-down" construction to to remove and replace tunnel roofs and walls

  • Three priority locations under roadways:

    • Tunnel beneath Byers Street (Phase 1)
    • Tunnel beneath West Johnson Street (Phase 2)
    • Tunnel beneath New Street (Phase 3)
Overall Map of Work Areas for the downtown tunnels. Purple highlights are on West Johnson and Byers Street and a blue highlight is on New Street where repairs will be performed.
PHASE 1: Byers Street (Starting Feb. 17)
PHASE 2: West Johnson Street (Projected 2026-2027)
PHASE 3: New Street (Projected 2026-2027)
Project Background
FAQs
Parking

Tunnel Repairs Progress

Updated on 03/19/2026 9:35 AM

This album shows the progress of the Downtown Tunnel Repairs Project

Creek Tunnel Assessment Photos

Updated on 09/19/2025 12:26 PM

Photos of creek tunnels from structural survey showing deficiencies

Looking Ahead: Long-term Creek Considerations

These tunnel repairs are separate from any future consideration of "daylighting" the creeks, opening the tunnels and exposing them to the surface. The city has allocated funding to study the feasibility of daylighting portions of the Wharf area, which would involve looking at different engineering approaches and costs. 

The current repairs focus on immediate structural safety needs and restoring full street functionality. Any future creek daylighting decisions would be made separately and would include extensive community input.